Project DiaryKey milestones and the activities undertaken by the Project Manager
November 2005
Stage One bid submitted
16/17 November 2005
Presentation at SCHOMS conference
January 2006
Stage Two bid submitted
March 2006
Bid approved by HEFCE
May 2006
Discussions with potential team members
10/11 May 2006
SCHOMS conference and project workshop
22 May 2006
Presentation at UPMG
June 2006
Finalisation of project team and consultancies
October 2006
- 15 telephone interviews for short case studies completed.
- 4 case studies outside HE completed.
- Technical solutions report and audit methodology being written
November 2006
Meeting of the project team to review progress and agree final list of the reports.
December 2006
Completion of the telephone interviews for the case studies.
February 2007
Detailed case studies finalised.
April-May 2007
Editing of the reports for consistency of content and appearance.
May 2007
- Presentation at the SCHOMS Conference
- Presentation at the University Print Managers’ Conference
July 2007
Finalisation and publication of the project outcomes.